Roofing change order, written while the roof is open.

Tear-off is when the estimate meets the real roof: a second layer nobody could see, decking that gives under your boots, fascia that crumbles when the drip edge comes off. The homeowner usually says yes over the phone. This form gets that yes on paper the same day.

Change order

Change order CO-2
Your Roofing Co.
Street address, City, ST
Phone · email
License no. (if your trade needs one)
Prepared forMaria LopezJob address
JobReroof, change order 1 to estimate E-118
DateDate
ItemQtyUnitRateAmount
Add: second layer tear-off
Estimate priced 1 layer. 2 found on the main roof
22square$35.00$770.00
Add: decking beyond the 3-sheet allowance
1/2 in. CDX, soft and delaminated sheets
9sheet$95.00$855.00
Add: replace rotted fascia, front eave
1x6 primed, painted to match
24linear ft$14.00$336.00
Add: remove skylight and deck over
Owner decision on site
1each$650.00$650.00
Credit: skylight reflash kit
No longer needed
-1each$185.00-$185.00
Subtotal$2,426.00
Tax (6.25%)$151.63
Change order total$2,577.63
Reason for change: a second layer of shingles and soft decking found during tear-off on [date]. Photos of each area sent to the owner before any work. Owner chose to remove the skylight rather than reflash it.
Approved by the owner by phone at [time] on [date] so the roof could be dried in the same day. This signed form confirms that approval.
Weather: if rain stops work, the roof is tarped and work picks up on the next dry day. No change to the price.
Payment: added to the balance due at completion.
Owner: ______________________ Date: ________ Contractor: ______________________ Date: ________
Track every job in Redline

Click any text to change it. Rates and the tax rate are examples, so put in your own. Totals update as you type.

What this template covers

  • Extra layers priced per square, the same unit as the estimate, so the math matches
  • Decking past the allowance per sheet, with the allowance named so it's clear what was already included
  • Fascia and trim by the linear foot
  • An owner decision made on the roof (the skylight) with its credit on the next line
  • The phone approval written down with a time, since you can't leave a roof open waiting for a signature

Doing it in Redline

From the roof, send the chat two photos and one line: "Lopez has a second layer, 22 squares at $35, and 9 more sheets past the allowance at $95." It builds the added lines as a quote on her file. Call her with one tap from her contact, then say "log a call with Maria Lopez, approved second layer and 9 sheets" so the approval is on her activity with the date. That's all on the Free plan.

She can't sign inside Redline, so get this form signed when you're down. Update the job value by chat, and the final invoice, with the change in its total, goes out as a card pay link (Solo, $29 a month). If it rains, "push the Lopez job to Thursday" moves the visit. The roofing invoice template shows how the decking line lands on the final bill.

Price the surprise before you climb down.

Redline is free to start. Photo plus one line, and the change is on her file.

Keep reading