Concrete change order, before the truck is called.

Once concrete is in the forms, nothing changes. So the change order happens at excavation: the apron is soft clay, the owner wants rebar after reading about cracks, and the stamped walk got cut for budget. Price it, sign it, then order the yards.

Change order

Change order CO-2
Your Concrete Co.
Street address, City, ST
Phone · email
License no. (if your trade needs one)
Prepared forGary FitzpatrickJob address
JobDriveway replacement, 4 in. slab, change order 1
DateDate
ItemQtyUnitRateAmount
Add: dig out soft subgrade at apron
Removed to firm soil, hauled off
6cu yd$65.00$390.00
Add: compacted gravel base to replace it
Placed in lifts, plate-compacted
9ton$48.00$432.00
Add: #4 rebar grid in place of wire mesh
Owner request, 18 in. on center, on chairs
640sq ft$0.85$544.00
Credit: stamped finish on front walk
Changed to broom finish
-120sq ft$6.00-$720.00
Subtotal$646.00
Tax (6.25%)$40.38
Change order total$686.38
Reason for change: soft clay found at the apron during excavation on [date]; the slab can't go on it as is. Owner asked for rebar in place of mesh and dropped the stamped walk to broom finish.
Pour date moves from [date] to [date], weather permitting. No pour below [temperature] or with rain in the forecast during finishing.
If the pour needs more concrete than the ordered [number] yards, the extra is billed at $[amount] per yard, delivered.
Keep vehicles off the new slab for [number] days. Saw cuts within 24 hours of the pour.
Owner: ______________________ Date: ________ Contractor: ______________________ Date: ________
Track every job in Redline

Click any text to change it. Rates and the tax rate are examples, so put in your own. Totals update as you type.

What this template covers

  • Excavation by the cubic yard and base by the ton, the units your supplier and hauler bill you in
  • Reinforcement changes priced across the slab by the sq ft
  • A finish downgrade as a credit, so the owner sees what the budget cut saved
  • A per-yard price for overage, agreed before the truck shows up short
  • Weather limits on the pour date, and when the car can go back on it

Doing it in Redline

Send the chat a photo of the apron with your probe stuck in it and "change order for Fitzpatrick: 6 yards dig-out at $65, 9 ton gravel at $48, rebar 640 sq ft at $0.85." It builds the added work as a quote on his file and can draft the email explaining why the apron has to be dug out, sent from your Gmail when you approve it. Keep the stamped-walk credit on this form.

Pour days move with the weather. "Push the Fitzpatrick pour to Tuesday 7am" moves it on the calendar, and Optimize can suggest moves for the rest of the week, grouped by town, that you apply if they work. When the slab's in, invoice it by chat with a card pay link on Solo ($29 a month). The concrete estimate app page covers how the original quote got built, and the concrete invoice template covers the final bill.

Settle it before the pour.

Redline is free to start. The change goes on his file by chat, and the pour date moves with one line.