GC change order with the subs and the markup on it.

On an addition, changes come from everywhere: the engineer's letter, the framing inspector, the owner's walk with the electrician, the plumbing selections that came in under allowance. This form puts them on one page with your overhead and profit shown.

Change order

Change order CO-2
Your Construction Co.
Street address, City, ST
Phone · email
License no. (if your trade needs one)
Prepared forRay and Denise KowalczykJob address
JobTwo-story rear addition, change order 4
DateDate
ItemQtyUnitRateAmount
Add: LVL header at family room opening
Per engineer's letter dated [date]. Includes temporary shoring
1each$1850.00$1,850.00
Add: recessed lights, family room
Electrical sub's price, owner request at the walkthrough
6each$210.00$1,260.00
Add: exterior hose bib, north wall
Plumbing sub's price
1each$340.00$340.00
Credit: plumbing fixture allowance not used
Allowance $3,200, owner selections came to $2,560
-1allowance$640.00-$640.00
Overhead and profit on added work
10% of the adds above
1lump sum$345.00$345.00
Subtotal$3,155.00
Tax (0%)$0.00
Change order total$3,155.00
Reason for change: the framing inspector required an engineered header at the family room opening (engineer's letter attached). Lights and hose bib requested by the owners on [date]. Fixture allowance reconciled against the owners' final selections.
Subcontractor quotes for the electrical and plumbing items are attached.
Schedule: adds 4 working days. Drywall start moves from [date] to [date].
Original contract: $[amount]. Change orders 1 to 3: $[amount]. This change order: total above. Revised contract: $[amount].
Payment: billed with the next draw. No work on these items proceeds until signed.
Owner: ______________________ Date: ________ Contractor: ______________________ Date: ________
Track every job in Redline

Click any text to change it. Rates and the tax rate are examples, so put in your own. Totals update as you type.

What this template covers

  • Changes that come from outside the owner: the engineer, the inspector, the plan reviewer, each with its paper trail named
  • Sub-priced work shown as the sub's number, with your overhead and profit as its own line instead of buried in the price
  • An allowance reconciliation credit when selections come in under, and the same line works for an overage
  • A numbered change order with the running revised contract total for the draw schedule
  • Schedule impact named by the trade it pushes, since that's the date the owner cares about

Doing it in Redline

Redline's memory picks up how you work without being told twice. Say "we put 10% overhead and profit on change orders" once, and next time you send "CO 4 for Kowalczyk: LVL header $1,850, six cans at $210 from the electrician, hose bib $340" it can build the quote with your markup line on it. It's saved on the owners' file, and the chat can draft the email to them, sent from your Gmail when you approve it.

On Team ($129 a month for 3 seats) the change goes into the job's notes and the crew sees it as office notes in the tech app, with a chat thread for that job. Techs never see prices, so the markup stays in the office. When the draw comes due, invoice it by chat with a card pay link (Solo and up). Redline doesn't produce AIA-style pay applications or lien waivers, so keep those where you keep them now. More on the general contractor page.

Keep the paper moving on every job.

Redline is free to start. Quotes by chat on every plan, invoicing on Solo, crew on Team.

Keep reading