Remodeling change order for what demo turned up.

You pull the sink base and the subfloor is soft. The same week she asks for under-cabinet lights and a pot filler, and decides to buy her own backsplash tile. One change order covers all three, with a reason for each.

Change order

Change order CO-2
Your Remodeling Co.
Street address, City, ST
Phone · email
License no. (if your trade needs one)
Prepared forTom and Priya HendersonJob address
JobKitchen remodel, change order 2
DateDate
ItemQtyUnitRateAmount
Add: replace water-damaged subfloor at sink base
3/4 in. plywood, glued and screwed. Hidden condition found at demo
32sq ft$14.00$448.00
Add: under-cabinet LED lighting with driver and dimmer
Owner request
14linear ft$38.00$532.00
Add: pot filler over range, rough-in and install
Owner-selected faucet, supplied by us
1each$850.00$850.00
Credit: backsplash tile material
Owner supplying tile. Install labor stays in the contract
-30sq ft$9.00-$270.00
Subtotal$1,560.00
Tax (6.25%)$97.50
Change order total$1,657.50
Reason for change: subfloor damage found under the sink base after demo on [date] (photos sent the same day). Lighting and pot filler added at the owners' request on [date]. Owners chose to supply their own backsplash tile.
Schedule: adds 3 working days. Cabinet install moves from [date] to [date]. Owner-supplied tile must be on site by [date] or the backsplash moves to the end of the job.
Payment: added to the next progress payment, due at cabinet install.
Contract total before this change: $[amount]. New contract total: $[amount].
Work on these items starts after both sides sign. All other contract terms stay the same.
Owner: ______________________ Date: ________ Contractor: ______________________ Date: ________
Track every job in Redline

Click any text to change it. Rates and the tax rate are examples, so put in your own. Totals update as you type.

What this template covers

  • A hidden condition line (rot, old wiring, a joist someone notched) kept apart from the owner's adds, so it's clear which costs they chose
  • Owner adds priced by the unit they're built in: subfloor by the sq ft, lighting by the linear ft, fixtures by the each
  • A credit for owner-supplied material, with the install labor left in the contract
  • The new date for the next trade in line, since one change on a kitchen moves everything after it
  • When the money comes in: rolled into the next progress payment, not a surprise at the end

Doing it in Redline

Take the photo of the soft subfloor and send it straight to the chat: "change order 2 for the Hendersons: 32 sq ft subfloor at $14, 14 ft of under-cabinet lights at $38, pot filler $850." Redline reads the photo, lays out the lines as a quote and saves it on their file. Attach the photos to the job too, so the before shot is there if anyone asks why the price went up.

Customers can't sign in Redline, so get this form signed or keep their written OK. Then say "bump the Henderson job to $48,350" so the pipeline and Home show the real contract, and when the kitchen's done, the final invoice goes out as a card pay link on Solo ($29 a month). The remodeling estimate and invoice templates cover the other two pieces of paper.