Your own work by the square foot, the subs as lump sums, the finishes as allowances, and your supervision on its own line. Edit the scope and the deposit follows.

Estimate

No. E-118
Your Construction Co.
Street address, City, ST
Phone · email
License no. (if your trade needs one)
Prepared forNate and Olivia BrooksJob address
JobBasement finish with full bath and egress window
Date · Valid forDate · 30 days
ItemQtyUnitRateAmount
Framing, walls and soffits900sq ft$5.00$4,500.00
Egress window and well1each$3800.00$3,800.00
Electrical (sub)
Lighting, outlets, bath fan
1lump sum$7800.00$7,800.00
Plumbing (sub)
Bathroom rough-in and set
1lump sum$6500.00$6,500.00
Drywall, hang and finish2800sq ft$2.60$7,280.00
Finishes allowance
Flooring, doors, trim, tile, fixtures
1allowance$14000.00$14,000.00
Project management and supervision1flat$4500.00$4,500.00
Permits1each$1200.00$1,200.00
Dumpster and cleanup2each$650.00$1,300.00
Subtotal$50,880.00
Tax (0%)$0.00
Estimate total$50,880.00
Deposit to book (10%)$5,088.00
Valid for 30 days. Deposit at signing, then progress payments at rough-in, drywall and final. Some states cap deposits; set yours to match.
Allowances are budgets. Selections over the allowance are billed by change order; under it, credited.
Hidden conditions (water, structural, old wiring) found after demo are quoted by change order before work.
Set tax to match how your state treats construction contracts.
Build it by chat in Redline

Click any text to change it. Rates and the tax rate are examples, so put in your own. Totals update as you type.

Why it's laid out this way

  • Your crew's work per sq ft, subs as lump sums
  • Finishes as an allowance, so the customer can choose without you re-quoting
  • Supervision priced openly instead of buried in every line
  • Payment schedule, allowances and hidden conditions spelled out in the terms
  • A deposit you can set to your state's limit

Or build it by chat

Tell Redline "quote the Brookses a basement finish: 900 square feet of framing, egress window, electrical sub $7,800, plumbing sub $6,500, 2,800 of drywall, $14,000 finish allowance, $4,500 supervision, 10% down" and it builds the itemized estimate on their file. Check every line before it saves.

There's no customer approval link in Redline today, so the contract and change orders still get signed your usual way. Redline holds the quote, the job and the follow-up. See the general contractor software page or the markup vs margin calculator.

Your next bid, built by chat.

Redline is free to start. Describe the scope and it lays out the lines and the deposit.

Keep reading