Excavation estimate template, for the wet backyard.

A homeowner job: regrade the yard and run a French drain to daylight. Machine hours as an estimate, materials by the yard, and a deposit to hold the date. Click any field to edit.

Estimate

No. E-118
Your Excavation Co.
Street address, City, ST
Phone · email
License no. (if your trade needs one)
Prepared forAlan WhitakerJob address
JobRegrade backyard and French drain to daylight
Date · Valid forDate · 30 days
ItemQtyUnitRateAmount
Mobilization1each$450.00$450.00
Skid steer with operator
Estimated, billed on actual hours
12hour$115.00$1,380.00
Mini excavator with operator
Estimated, billed on actual hours
6hour$150.00$900.00
Trenching, French drain
To daylight at the back line
120linear ft$12.00$1,440.00
Washed drain stone12cubic yard$55.00$660.00
Loam, spread and graded20cubic yard$45.00$900.00
Haul-off2load$300.00$600.00
Subtotal$6,330.00
Tax (0%)$0.00
Estimate total$6,330.00
Deposit to book (25%)$1,582.50
Valid for 30 days. 25% deposit books the job; balance due on completion.
811 marks requested before we dig, and we wait for every utility to respond. Private lines (irrigation, pet fence, lamp posts, septic) aren't marked: flag them or tell us where they run.
Hourly lines are estimates and billed on actual machine hours. Rock or buried debris billed at the hourly rate plus haul-off.
Wet ground can push the start. Any grading or erosion control permit the town requires is priced separately.
Build it by chat in Redline

Click any text to change it. Rates and the tax rate are examples, so put in your own. Totals update as you type.

Why it's laid out this way

  • Machine time per hour, marked as an estimate so the final bill isn't a fight
  • Trench per linear foot, stone and loam per cubic yard
  • Haul-off per load, the way the trucking actually costs you
  • Dig-safe marking and private lines spelled out in the terms

Or build it by chat

Send Redline a photo of the standing water and say "quote Alan Whitaker: mobilization, 12 hours skid steer, 6 hours mini, 120 ft French drain, 12 yards stone, 20 yards loam, 2 loads out, 25% deposit". It builds the estimate and saves it on his file.

There's no online approval link, so get his yes by phone or email, then bill the deposit on Solo. Locate tickets expire, so ask Redline for the first open day after the marks are in. See quotes and estimates or the hourly rate calculator.

Quote it before the next rain.

Redline is free to start. Say the machines, the hours and the yards, and it builds the estimate.